下面是小编为大家整理的某公司码头试运行经营方案,供大家参考。
某公司码头试运行经营方案 编制:
批准:
x xxxx 有限公司 7 2017 年 年 8 8 月 月 0 20 日 目 录 一、 建设项目施工完成情况 ··························· 1 1 1.1 建设项目简介 ···································· 1 1.2 项目施工完成情况 ·································· 1 1.6 码头管道走向 ···································· 3 1.7 码头管道简述 ···································· 4 1.8 码头工艺流程说明 ·································· 8 1.9 本项目与其它场所的距离情况表 ···························· 16 1.10 危险有害因素情况 ·································· 17 二、试车目的 ································ 18 三、 码头 设计输送能力 ···························· 19 四、试车组织、试车负责人及 人员职责 ····················· 19 4.1 试运营组织准备工作 ································· 19 4.2 指挥部要紧职责: ··································· 20 4.3 各部门职责 ····································· 20 4.4 试运营人员安全培训、工艺交底、岗位操作培训情况 ··················· 21 五、试车务必具备的条件 ··························· 22 5.1 工程项目中间交接 ·································· 22 5.2 条件准备:
····································· 22 5.3 联动试车 ······································ 22 5.4 人员培训 ······································ 23 5.5 生产管理制度 ···································· 23 5.6 试车方案 ······································ 23 5.7 保运工作 ······································ 24 5.8 供电系统 ······································ 24 5.9 备品配件 ······································ 24 5.10 通讯联络系统 ···································· 24 5.11 物料贮存系统 ···································· 25 5.12 安全、消防、急救系统 ································ 25 5.13 生活后勤服务 ···································· 25 六、试车所需准备工作及需检查内容的目录 ··················· 25 七、试车所需外部协作条件及临时设施的方案 ·················· 26 八、试车物资清单 ······························ 27 8.1 水、电、气 ····································· 27 8.2 管道用备品备件 ··································· 27 九、试车程序及进度表 ···························· 28 9.1 试车过程中应关注的重要问题 ····························· 28 9.2 试车程序 ······································ 28 9.3 试车条件 ······································ 28 9.4 试车要求 ······································ 29 9.5 试车前的准备工作 ·································· 29 9.6 试运营进度表 ···································· 30 9.7 试车的总结与评估 ·································· 31 十、开车、停车及紧急情况的处理程序与要求 ·················· 32 10.1 注意事项 ······································ 33 10.2 正常开停车 ····································· 34 10.3 正常停车 ······································ 37 10.4 紧急停车 ······································ 38 十一、 码头试运营过程 中可能出现的安全隐患与计策措施 ············· 38 11.1 特殊情况参照表 ··································· 40 十二、 试 运营 过程中的事故应急救援预案 ··················· 40 12.1《码头专项应急预案》 ································ 40 12.2《压力管道专项预案》 ································ 40 12.3《环保专项应急预案》 ································ 40 十三、建设项目周边环境与建设项目安全试 运营 影响确认情况 ··········· 41 13.1 项目周边生产经营活动与居民生活情况 ························· 41 13.2 试运营过程发生火灾、爆炸事故影响 ·························· 41 13.3 告知义务 ······································ 41 十四、危险化学品重大危险源监控措施落实情 况说明 ··············· 42 14.1 本项目危险化学品重大危险源的辨识 ·························· 42 十五、试 运营 起止日期 ···························· 44 十六、附件 ································ · 45 F1.0 消防设施培训 ···································· 45 F2.0 操作规程现场培训 ·································· 45 F3.0 应急预案培训 ···································· 45 F4.0 管道投用确认单 ··································· 46 F5.0 开工条件确认表 ··································· 47 F6.0 装置开工审批表 ··································· 48 十七、作业过程风险分析 ··························· 49 17.1 作业风险评价标准 ·································· 42 17.2 风险等级评定 ···································· 42 17.3 作业风险分析表 ··································· 43 方案会签表 序号 职 务 签字栏 日期 1 1 生产部工程师 2 2 车间副主任 3 3 车间主任 4 4 生产部长 5 5 设备部长 6 6 安全部长 7 7 总工程师 8 8 生产副总 批准(总经理):
年 月 日 一、 建设项目施工完成情况 1 1.1 建设项目简介 (1)项目名称:
(2)项目性质:新建 (3)投资规模:
(4)安全投入:
0 万元 (5)项目地址:
(6)建设单位:
(7)法定代表人:
(8 项目建设用地:
㎡ (9)人员编制:16 人,其中 1 人/班(压力管道巡线员) 2 1.2 项目施工完成情况 1.2.2 该项目于 201 年 月底完成施工安装,与 201 年 月份中交。施工中严格按照图纸工艺要求与国家有关规定施工。
1.2.3 项目涉及的压力管线都通过江苏省特种设备安全监督检验研究院检验合格,压力表经 市计量测试技术研究所检测合格,取得检测证书。防雷接地系统委托 市防雷安全管理中心检测合格,取得了检测报告;可燃有毒气体均调校完毕;试运营所需的水、电、气能满足试运营的需要;试运营场所已清理干净,满足试运营的需要;安全、环保工程设施已全部竣工,将与码头项目工程同步进行试车。
1.2.4 该项目已完成了管道的试压、气密、吹扫、仪表调校、动设备试机等工作,苯与苯 xx 管道还进行了通球试验。设计、监理、施工及建设单位四方已经签署了竣工验收证书,项目施工质量符合设计要求与有关规范要求,已具备试运营的条件。
xx 码头 130m 引 223m 引桥 25m 452.814m 223m 综合 综合 xx 2 万吨级 2 万吨级 2#平台 191m 60m 18m 690m 拆船厂码头夹江 60m 1#平台 65m 44.7m 500t 1.3 3 总平面布置 1.3.1xx 码头扩建码头岸线长度为 190m,xx 码头与 xx 公司码头净约距约为 321.4m,其中 xx 公司上游端 70m 岸将作为其扩建、改造岸线,其有关手续正在进行。由于码头位于东夹江长江入口处,为不影响东夹江内河岸线开发后其船舶进出及充分利用 xx 码头与 xx 之间的深水岸线,xx 码头 190m 岸线分两部分,分别位于 xx 化学码头平台上下游两端,设有 2个靠船、作业平台,上游端平台长度为 60m,下游端平台长度为 130m。码头下游与 xx 公司码头口门宽度为 121.4m。在下游 2#码头内档布置 1 个 500DWT 化学品泊位。
上游端 60m 码头平台宽度与 xx 码头作业平台一致,为 18m;考虑内侧内港池靠泊 500t化学品船安全距离及码头装卸作业要求,下游端 130m 码头平台宽度为 25m。
码头引桥位于原 xx 靠船作业平台与新建 2#靠船、作业平台交界处。在引桥上游侧布置一个 22.1mX15.6m 的综合用房平台,与 2#靠船平台距离为 50m。
1.3.2 装卸工艺 装卸工艺根据总平面布置分别设置 1 个外档 20000DWT 泊位与 1 个内档 500DWT 泊位,两个码头泊位货种统筹兼顾。码头配备 6 根主管线,引至外档 20000DWT 泊位,在内、外档两个泊位间设有 4 根机动联通管线连接。装卸工艺根据总平面布置整体向上游平移 60m 设置了一个 20000DWT 主泊位,可兼靠 2 个 20000DWT 泊位。
1.4 4 地理位置 xx 码头扩建码头位于长江下游扬中河段太平洲左汊团结闸下游处,如泰运河河口上游1.1km 处,其下游为江苏 xx 物流有限公司化工码头,上游为泰州 xx 仓储有限公司码头,后方紧临 xx 市经济开发区。码头中心区域地理坐标为东经 119°54′,北纬 32°10′,水路距吴淞口约 203km。
5 1.5 周边环境 xx 码头 xx 码头扩建码头位于 xx 港区过船作业区,xx 港区过船作业区是专业化液体化工港区,要紧为 xx 市经济开发区服务,以化工品运输为主,码头上游紧邻团结河,位于已建成的泰州 xx 码头处,与下游 xx 散货码头距离为 191.4m。
6 1.6 码头 管道走向 序号 管道名称 物料走向 1 xx 卸船预冷管线(DN80) 码头引桥根部 1#号柱至装卸平台 2 xx 卸船管线(DN250) 装卸平台至码头引桥根部 1#号柱 3 xx 卸船预冷管线(DN80) 装卸平台至码头引桥根部 1#号柱 4 苯 (DN300) 装卸平台至码头引桥根部 1#号柱 5 苯 xx (DN300) 装卸平台至码头引桥根部 1#号柱 6 苯(250) 码头引桥根部 1#号柱至装卸平台 7 机动管线 1# 内泊位至计量撬 8 机动管线 2# 内泊位至计量撬 9 机动管线 3# 计量撬至内泊位 10 机动管线 4# 计量撬至内泊位 11 长江清水(DN400) 综合楼西侧取水口至码头引桥根部 1#号柱 12 消防水 (DN400) 码头引桥根部 1#号柱至装卸平台 13 污水 (DN150) 装卸平台至码头引桥根部 1#号柱 14 生活给水(DN150) 码头引桥根部 1#号柱至装卸平台 15 氮气 (DN80) 码头引桥根部 1#号柱至装卸平台 7 1.7 码头 管道简述 1、苯管线 1 根(DN300);区域...